Bina Commercial Renovation Expert’s free renovation timeline planner estimates how many weeks your renovation needs from brief to handover and works back from your opening date.
How the timeline is estimated
The planner adds five stages: survey and brief, design and drawings, approvals, site works and handover. Design and approval weeks depend on how big the changes are. Site weeks grow with floor area and differ by type of premises, and they stretch by about 30% when noisy work is allowed only after hours.
| Changes | Design | Approvals |
|---|---|---|
| Cosmetic only: paint, flooring, loose furniture | 1–2 weeks | 1–2 weeks |
| New layout, ceiling or M&E changes | 2–4 weeks | 2–4 weeks |
| Structural, facade, change of use or fire services | 3–5 weeks | 4–6 weeks |
Site works, before the after-hours allowance: office 4–16 weeks, shop / retail 3–10 weeks, restaurant / café 5–16 weeks, clinic 5–14 weeks, factory / warehouse 4–24 weeks, depending on floor area.
The office fit-out timeline guide explains each stage and the usual causes of delay, and the mall shop fit-out guide covers night works and landlord inspections. Approvals for your premises are listed by the renovation permit checker.
These are estimates. The real programme is fixed after the site survey, once the building’s rules and long-lead items are known, so ask our admin before you sign a tenancy or announce an opening date.
FAQ
Timeline planner questions
How long does a commercial renovation take in Malaysia?
As an estimate, a typical office fit-out takes about 10 to 20 weeks from brief to move-in, and a mall shop about 3 to 8 weeks on site once the unit is handed over. Restaurants and clinics take longer because of kitchen and clinical services. The real programme is set after a site survey.
What delays a renovation most?
Late design changes, slow building or council approvals, long-lead items such as custom glass and imported furniture, and buildings that allow noisy work only after hours.
Can approvals and design overlap?
Often, yes. Building and council submissions can run in parallel, and some works such as site protection can start early if the building agrees in writing. The planner shows the stages one after another, so the real programme can be shorter.
More free planning tools
Tell us about your space
Send the address, the floor area and what the space needs to do. We arrange a site survey and give you a quotation you can compare line by line.
Usually starts from RM30,000 depending on project (need custom quote to be fair based on site condition & scope).
Planning first? Try the free cost calculator or scope builder.
Any question or technical correction — our admin is ready to help. You can ask directly through our official WhatsApp.