Defects Liability Period by Bina Commercial Renovation Expert

Planning, Budget & Contracts

Bina Commercial Renovation Expert Defects Liability Period

Bina Commercial Renovation Expert on Defects Liability Period: The defects liability period is the time after handover — commonly 6 to 12 months in commercial renovation — during which the contractor must return and fix defects caused by workmanship or materials. Retention money held back from payments gives the contractor a reason to respond promptly.

Updated 29 November 2026 · 5 min read · Published by Bina Integrated Technology Sdn. Bhd.

How the defects liability period protects you after handover

Short answer

What counts as a defect?

A defect is work that does not meet the contract: cracked partitions, leaking pipes, doors that stick, failing paint, lights that flicker. Damage caused by the occupant, normal wear or changes made by others is not a defect.

How should defects be reported?

Report in writing, with photos and the location, as soon as you notice. Contractors usually inspect and fix defects in batches, with urgent items such as leaks handled immediately. Near the end of the period, do a joint inspection and list anything outstanding.

  • Report in writing with photos
  • Mark urgent items clearly
  • Keep a defects log
  • Joint inspection before the period ends

How does retention work?

Retention is a small percentage of each payment held back. Half is often released at practical completion, and the rest when the defects period ends and defects are cleared. See the contract checklist for how to write it in.

What is not covered by the defects liability period?

The defects liability period covers faults caused by workmanship or materials. It does not cover damage from misuse, normal wear, alterations made by the owner or other contractors, or consumables such as lamps and filters once they are in use.

The line between a defect and wear is clearer when the handover records the condition of the space. Photos and a signed handover list at completion settle most later arguments. The renovation contract checklist shows how the defects period is written into the contract.

What happens at the end of the defects liability period?

At the end of the defects liability period, the owner and contractor inspect the space together and list any defects still open. Once those are fixed, the contractor receives a certificate of making good defects and the remaining retention is released.

Owners should note defects throughout the period rather than only at the end. Our shop renovation clients report defects through one channel so nothing is lost between the shop floor and the contractor.

How are defects in M&E services handled?

Defects in M&E services, such as air-conditioning, power and plumbing, often depend on equipment warranties from the manufacturer as well as the contractor’s workmanship. The handover file should list each warranty and its start date.

  • Equipment warranties registered in the owner’s name
  • Maintenance schedule needed to keep each warranty valid
  • Contact for the contractor’s defects team
  • Test certificates such as Form G and Form H for electrical work

Illustrative example: a defect reported and fixed

Illustrative example, not a client project: four months after a shop opens, a section of vinyl flooring starts to lift near the entrance. The owner photographs it and reports it through the contractor’s defects channel with the date and location.

The contractor inspects, finds the adhesive failed where water came in under the door, and replaces the section. The threshold is also resealed so the cause is fixed. The repair is recorded in the defects log, and at the end of the defects period the joint inspection finds nothing open, so the retention is released.

Which defects period mistakes cost owners?

Owners lose the protection of the defects period in a few predictable ways.

  • Reporting defects verbally with no written record
  • Asking another contractor to fix defects first
  • Releasing retention before the final inspection
  • Losing the warranty documents for equipment

Who is responsible for what during the defects liability period?

The defects period works when both sides follow a simple routine.

  • Owner: records defects in writing with photos and dates.
  • Contractor: inspects, fixes defects caused by workmanship or materials, and fixes the cause.
  • Equipment suppliers: honour warranties registered in the owner’s name.
  • Maintenance team: keeps services maintained so warranties stay valid.
  • Both parties: inspect together at the end of the period before retention is released.

Which defects terms appear in renovation contracts?

These terms describe what happens after handover.

  • Defect: a fault caused by workmanship or materials that do not meet the contract.
  • Defects liability period: the period after handover during which the contractor must fix defects.
  • Retention: money held back from payments as security for fixing defects.
  • Certificate of making good defects: confirmation that reported defects have been fixed.
  • Latent defect: a hidden defect that appears only after some time.

What should you ask about defects before signing?

These questions set expectations for after-handover support.

  • How long is the defects liability period?
  • How do I report a defect and how quickly will you respond?
  • How much retention is held and when is it released?
  • Which equipment warranties will be handed over?

Step-by-step

  1. 1 Agree the period length in the contract.
  2. 2 Set retention terms.
  3. 3 Log defects with photos.
  4. 4 Hold a joint final inspection.
  5. 5 Release retention when cleared.

Checklist

  • Period length stated
  • Retention terms set
  • Defects log kept
  • Final inspection held

Key takeaways

  • Defects periods commonly run 6–12 months.
  • Report defects in writing with photos.
  • Retention encourages prompt fixes.

Defects Liability Period: common questions

How long is the defects liability period in commercial renovation?

The defects liability period is commonly 6 to 12 months in commercial renovation, and the exact length is set in the contract.

Who pays to fix defects during the defects period?

The contractor pays to fix defects caused by workmanship or materials. Damage from misuse or later alterations is the owner’s cost.

Can I withhold payment for defects?

The retention sum held under the contract exists for this purpose. Withholding other payments should follow the contract terms to avoid a dispute.

What is a certificate of making good defects?

It confirms that defects reported during the defects liability period have been fixed, and it usually triggers the release of the remaining retention.

Does the defects period start at handover?

Usually yes. The contract defines the start, normally the date of practical completion or handover.

What is a latent defect?

A latent defect is a hidden fault that is not visible at handover and appears later, such as a concealed leak.

Author Faiz Azizan (PhD) works as SEO author & researcher for commercialrenovation.my with Google KG. Contact via LinkedIn or web: drfaizazizan.com.

Tell us about your space

Send the address, the floor area and what the space needs to do. We arrange a site survey and give you a quotation you can compare line by line.

Usually starts from RM30,000 depending on project (need custom quote to be fair based on site condition & scope).

Planning first? Try the free cost calculator or scope builder.

WhatsApp +60 13-340 7007

Any question or technical correction — our admin is ready to help. You can ask directly through our official WhatsApp.